Work Plan

Gantt chart – Timing of the different work packages and their components

Deliverables

D6.1 Minutes from the kick-off meeting with the main conclusions WP6 Month 2
D1.1 Report on the setup and validation of the Hg speciation methods WP1 Month 6
D5.1 Website and social media accounts of the project WP5 Month 6
D1.2 Report on the setup and validation of the Cr speciation methods WP1 Month 8
D1.3 Report on the setup and validation of the Se speciation methods WP1 Month 9
D1.4 Report on the setup of fractionation methods WP1 Month 10
D1.5 Report on the setup and validation of the Sn speciation methods WP1 Month 12
D6.2 Minutes from the second Project Meeting WP6 Month 13
D1.6 Report on the setup and validation of the As speciation methods WP1 Month 16
D2.1 Technical report on site and fish species selection and on sampling activities WP2 Month 20
D3.1 Technical report of sample collection WP3 Month 20
D6.3 Minutes from the third Project Meeting WP6 Month 25
D4.1 Pre-draft of the review on legislation of food safety WP4 Month 30
D2.2 Pre-draft of the biological and environmental effects on metal species presence in the edible tissues of fish WP2 Month 36
D3.2 Pre-draft of the effect of season, temperature and substrata type on the presence of different metal species in the edible tissues of farmed fish WP3 Month 36
D4.2 Pre-draft of the comparison of risks and benefits for humans based on total metal content versus different metal species WP4 Month 36
D4.3 Pre-draft of the biological, environmental and seasonal effects on the risks and benefits for humans by consuming fish WP4 Month 36
D5.2 Report on the final workshop WP5 Month 36
D5.3 Presentations at conferences and/ or pre-drafts of publications WP5 Month 36
D6.4 Minutes from the final Project Meeting WP6 Month 36